|
Consequences of not providing a payment schedule
Section 19 of the Act describes the consequences, and liability, of respondents not providing a payment schedule within the time required by the Act. If a respondent does not provide a payment schedule they become liable to pay the claimed amount, the claimant has access to the following resolutions:
- They may make an adjudication application to the RICS DRS under section 21(1)(b) of the act.
- They may serve a notice of their intention to suspend work or supply of related goods under the contract. The applicable section of the Act is section 33.
- They may begin recovery of the unpaid portion of the claimed amount from the respondent as a debt owning to the claimant, in any court of competent jurisdiction. If the claimant starts proceedings with this method, the respondent is not entitled to bring any counter claim against the claimant, or raise any defence in relation to matters arising under the construction contract
The case of Walter Construction Group Ltd V CPL (Surry Hills) Pty Ltd [NSWSC] is a good example of the potential consequences for respondents when they fail to provide a valid payment schedule.
Consequences of not paying of an amount set out in a payment schedule
Section 20 of the Act describes the consequences, and liability, of respondents not paying an amount set out in a payment schedule within the time required by the Act. If the respondent fails to pay an amount due to the claimant that has been set out in a payment schedule, then the claimant has the following options:
- They may make an adjudication application to the RICS DRS under section 21(1)(a)(ii) of the Act.
- They may serve a notice of their intention to suspend work or supply of related goods under the contract. The applicable section of the Act is section 33.
- They may begin recovery of the unpaid portion of the claimed amount from the respondent as a debt owning to the claimant, in any court of competent jurisdiction. If the claimant starts proceedings with this method, the respondent is not entitled to bring any counter claim against the claimant, or raise any defence in relation to matters arising under the construction contract
Effect of providing a valid payment schedule in regards to adjudication
A valid payment schedule is a valuable defence for respondents in the case of an adjudication application. Section 24(3) of the Act states, "the respondent may give the adjudication response to the adjudicator only if the respondent has served a payment schedule on the claimant withing the time specified. 24(4) of the Act states, The respondent can not include in the adjudication response any reasons for withholding payment unless those reasons have already been included in the payment schedule served on the claimant.
The Adjudication Response is the respondent's official response to a claimant's adjudication application, which functions as the respondent's reply to the adjudication application and can clarify issues of non-payment as per the payment schedule. For more information on the adjudication response go to >> Submitting the Adjudication Response
|